DESTIN AIRPORT RUNWAY RECONSTRUCTION


Project Description

Contract Name:   Destin Airport Runway Reconstruction
Location:   Destin, FL

Highlights

The project required all work on the runway to be done during a 7 day shutdown period. We were able to complete the project in 10 days after 3 days of rain delayed the scheduled opening. 3D paving was performed by using 6 total stations and 2 paving crews placing asphalt in tandem to prevent cold longitudinal joints.

Scope of Work

This runway was milled and resurfaced to a new profile to correct slopes. New runway lighting system was installed as well as shoulder regrading and sodding.